CONCRETE CUTTING, CORING, CHASING & DRILLING PERMIT
Note: This permit is to be completed for all penetrations exceeding 40mm in depth
Structural Considerations
Services Considerations
Have all identified services been located and marked?
Note: A copy of the site service plan (mud map) is to be attached to the permit.
Services Trades Sign Off [insitu concrete elements only]
Service trades (i.e. electrician, plumber, etc) are required to complete the section below as acknowledgement they have reviewed the permit conditions and locations and that there are no services or services have been isolated within the work area. (Note: If subcontractor is not available, an email confirmation may be attached)
Electrical Subcontractor
Plumbing
Other
Other
HSE Considerations

Works must not commence if ‘No’ has been identified in any of the above sections works until all 'No' items have been rectified.

Permit Reviewer